For a better experience, click the Compatibility Mode icon above to turn off Compatibility Mode, which is only for viewing older websites.

Drexel Health Sciences Building Updates

April 8, 2022

Click to enlarge photos

April 2022

Sidewalk leading to nearly complete-looking Health Sciences Building facade

Sidewalk leading to nearly complete-looking Health Sciences Building facade

February 2022

Health Sciences Building level 3

Health Sciences Building Level 3

Health Sciences Building Level 3

Health Sciences Building level 3

Health Sciences Building level 6

Health Sciences Building level 6

Health Sciences Building level 12

Health Sciences Building level 12

Health Sciences Building Level 11

Health Sciences Building roof

Health Sciences Building roof

January 2022

The Health Sciences Building is going strong. The steel stud framing is beginning on level 12, the final floor! Drywall is completed up through level 8 with the medical gas systems installed and tested on levels 7 and 8.

The service elevators (cars 11 and 12) will be up and running for construction use within the next six weeks.

Tower cranes have been removed, and they will begin removing the hoist and closing up the curtain wall panels immediately after the elevators start up.

Carpet install is to begin February 1. Resinous flooring on level 12 (anatomy spaces) will begin March 11, and the finishes trades are scheduled to begin once space is temperature controlled.

Click to enlarge photos.

Ground floor of the Health Sciences Building looking north

Health Sciences Building 300 Person Active Classroom view looking east

Health Sciences Building third floor classroom looking east

Health Sciences Building fourth floor

Health Sciences Building fifth floor - booth alcove

Health Sciences Building sixth floor community breakout space in the center of the building

Health Sciences Building twelfth floor looking from west to east end of building

Health Sciences Building penthouse

December 2021

The Health Science Building now has permanent power, and it is watertight with curtain wall (exterior) completed. The service elevators should be operational by early March, and the passenger cars up and running by end of March. The flooring installation should be starting on the second floor within three weeks. The HVAC system chilled beam has been installed up to the fourth level. Things are moving along!

Click to enlarge photos.

Exterior of Health Sciences Building

Exterior of Health Sciences Building

Exterior of Health Sciences Building

Exterior of Health Sciences Building


October 2021

Construction on our future home is moving along! The building perimeter is almost complete and should be “zippered up” by the end of November.

Core and shell work (elevators, toilet rooms and stairs) are really taking shape. The HVAC work is in place, metal stud installation is up to the 12th floor and drywall work is underway on the lower floors. Visible spaces and rooms are replacing the big empty floors. Interior photos to come soon.

Click to enlarge photos.

photo from ground looking up at new health sciences building mid-construction

distance photo from end of sidewalk of new health sciences building with cranes on roof


June 2021

Photo of Drexel Academic Tower construction

May 2021

Cement trucks ready to start pouring concrete floors of the new building.

Cement trucks ready to start pouring concrete floors of the new building.

March 2021

Six cement trucks lined up to pour the concrete floors.

Cement trucks ready to start pouring concrete floors of the new building.

Cement trucks ready to start pouring concrete floors of the new building.

Click images to magnify


January 2021

Photo of Drexel Academic Tower construction 

Photo of Drexel Academic Tower construction 

Photo of Drexel Academic Tower construction


December 2020

When the announcement about a new home for the College of Nursing and Health Professions was made in May 2019, no one could have imagined that construction would be delayed by a global pandemic. It was expected that groundbreaking would be in spring 2020 with a substantial completion delivery of mid-2022. Beginning in late July, it is still the hope to maintain the same timeline.

Google Earth screenshot of the location of the Drexel Academic Tower

With CNHP being the first occupants of the new facility, some of the College of Medicine’s administrative functions, the Graduate School of Biomedical Sciences and Professional Studies and its first- and second-year medical program will join the College in phases. President Fry, in a message to the University in late 2019, said “at the new academic building, many of Drexel’s health-related programs will be under one roof, enhancing opportunities for interdisciplinary education in a facility that affords health sciences students, faculty and professional staff the best possible environment for continued development and growth.”