STAR Review Timeline: Phase I
The Huron Team began in December 2012 to collect data through their confidential online survey and conduct on-campus interviews about Drexel’s organizational structure, policies, procedures, and budgeting and staffing. Phase 1 will extended over 17 weeks, resulting in a series of recommendations for operational effectiveness and an implementation plan to be carried out in Phase 2.
Phase 1:
Activity
|
Week
|
Launch
data and interview requests, scope
finalization, logistics |
1 |
Discover
Initial benchmarking and data analysis,
interviews with stakeholders campus-wide |
2-6 |
Analyze
Detailed evaluation, development of
prioritization methodology |
7-11 |
Develop
Creation of business cases, vetting with key
University staff and stakeholders |
12-16 |
Evaluate
Prioritization of opportunities, high-level
implementation planning |
17 |