STAR Review Timeline: Phase I

The Huron Team began in December 2012 to collect data through their confidential online survey and conduct on-campus interviews about Drexel’s organizational structure, policies, procedures, and budgeting and staffing. Phase 1 will extended over 17 weeks, resulting in a series of recommendations for operational effectiveness and an implementation plan to be carried out in Phase 2.

Phase 1:

Activity
Week
Launch
data and interview requests, scope
finalization, logistics
1
Discover
Initial benchmarking and data analysis,
interviews with stakeholders campus-wide
2-6
Analyze
Detailed evaluation, development of
prioritization methodology
7-11
Develop
Creation of business cases, vetting with key
University staff and stakeholders
12-16
Evaluate
Prioritization of opportunities, high-level
implementation planning
17