Current Projects

Construction Scene

Major Drexel Project Updates as of March 2018

32nd and Market Street Intersections (former Firestone site): Construction began in March to reconfigure the intersections around the former Firestone property. This work will improve pedestrian safety across Market Street and JFK Boulevard and provide a new, signalized crosswalk at Lancaster Walk. The vacation of the portion of Lancaster Avenue bordering the former Firestone site, and the University’s acquisition from the city of the vacated street and the adjacent landscaped triangle, are contingent on the completion of this work, which is expected in fall 2018. During construction, the former Firestone property will be fenced off, the sidewalk will be closed on the north side of Market Street between 32nd Street and JFK Boulevard, and a portion of N. 32nd Street will be closed to vehicle traffic. Please use caution and expect delays when traveling through the area.

Armory (Lancaster Avenue Readiness Center): Work continues on exterior restoration and improvements to the Armory building. This work will include masonry restoration, new roofing and restoration of all windows along 32nd and 33rd Streets, Lancaster Walk and the half-round windows along Cuthbert Street. Funded jointly by the state and by Drexel, this project is managed by Pennsylvania's Department of General Services and is expected to continue into the fall.

Bernhardt Memorial Courtyard at Thomas R. Kline School of Law: Construction is nearly complete on the Bernhardt Memorial Courtyard, located on Market Street between the Kline School of Law and Hagerty Library. Designed by Studio Bryan Hanes, the courtyard provides an intimate outdoor space to study and socialize.

Bossone Research Enterprise Center Renovations: Permitting is underway for the renovation of an existing laboratory on the third floor to increase usability for chemically intensive work related to energy and energy storage. Construction is expected to commence in summer 2018.

Center for Automation Technology: Construction for environmental engineering laboratory facilities related to work in energy and the environment is scheduled for FY’19 (Phase 2) and FY’20 (Phase 3).

Fox Historic Costume Collection : Construction is in progress on the expansion of the Robert and Penny Fox Historic Costume Collection in the URBN Center, with completion expected in late spring 2018.

Korman Center Facade: Remedial work on the north, south and west facades of the Korman Center building is expected to be complete in late May 2018.

Third-Party Project Updates as of March 2018

Summer 12 Townhomes (Radnor Property Group): Construction is in progress on Radnor Property Group’s “Summer 12” – a dozen new owner-occupied townhomes along the 3200 block of Summer Street. The townhomes are expected to be complete in spring 2018.